FERC Involvement In Southern’s South System Expansion III Project

The Federal Energy Regulatory Commission (FERC) is the lead federal agency responsible for authorizing the South System Expansion III Project under the National Environmental Policy Act (NEPA). On March 4, 2008, the FERC assigned pre-filing Docket No. PF08-13-000 to the South System Expansion III Project. Interested parties who wish to correspond with FERC about this project should refer to this docket number. Comments provided to the FERC under this process will be addressed by the FERC in its project evaluation. Persons may file comments with the FERC electronically through their website or they can mail them (send original and 14 copies ) to the following address:

     Kimberly Bose, Secretary
     Federal Energy Regulatory Commission
     888 First Street, N.E.
     Washington, DC 20426

Additional information about the FERC and the NEPA environmental review process can be obtained through the FERC Web site.

FERC Filing

Southern Natural Gas Company (SNG) filed the original application for a certificate to construct the South System Expansion III Project (SSEIII) on December 15, 2008, and filed an amendment to that application on February 10, 2009. SNG received it’s FERC certificate for SSEIII on August 27, 2009, and filed its’ acceptance of that certificate on September 1, 2009.

On September 18, 2009, Southern filed an Implementation Plan for construction of its Plant McDonough Meter Station (Meter Station) and Phase I warehouse yards, and requested authorization to begin construction at these locations. By letter order dated November 5, 2009, the Commission approved for Southern to commence construction at these locations. On April 20, 2010, Southern requested authorization to commence partial service at the Meter Station. Following receipt of Commission authorization by letter order dated April 28, 2010, Southern commenced partial service at the Meter Station on May 1, 2010.

On November 24, 2009, Southern filed an Implementation Plan for construction of its Phase I Pipeline facilities, and requested authorization to begin construction at these locations. By letter order dated January 21, 2010, the Commission approved for Southern to commence construction at these locations.

As part of Phase II of the SSEIII Project, the Commission authorized Southern to install an additional 10,310 horsepower compression at its existing Bay Springs Compressor Station (“Station”) located in Jasper County, Mississippi. On April 8, 2010, Southern requested authorization to begin certain modifications within the Station boundaries in preparation for the installation of the additional horsepower at the Station. By letter order dated April 13, 2010, the Commission approved for Southern to commence construction at this location.

On May 14, 2010, Southern filed an Implementation Plan for construction of its Phase II warehouse yards, and requested authorization to begin construction at these locations. By letter order dated May 27, 2010, the Commission approved for Southern to commence construction at these locations.